Inner Harbor desalination and water supply
Where it standsThe Inner Harbor seawater desalination plant is stalled after the council rejected its design contract on Sept. 1, 2026.
What's on the tableWhether to revive the Inner Harbor plant, pursue desalination elsewhere, or rely on other new water supplies.
- On Sept. 1, 2026, the council voted 5-3 against a $78.6 million contract with Corpus Christi Desal Partners to advance the Inner Harbor plant's design. Corpus Christi Caller-Times · Sep 17, 2026
- The plant was planned to produce up to 30 million gallons of treated water per day, at an estimated cost of $979 million. Corpus Christi Caller-Times · Sep 17, 2026
- In February 2026 the council voted 5-3 to negotiate a design-build contract for the plant with Corpus Christi Desal Partners. City Council minutes, Feb. 24, 2026 · Feb 24, 2026
- In June 2026 the council voted 7-2 to table the design-build contract until Sept. 1. City Council special meeting minutes, June 2, 2026 · Jun 2, 2026