Preston Way bridge replacement
Where it standsThe village is waiting for the state Department of Transportation to approve plans so a bid can go out.
What's on the tableThe next board will oversee bidding, the final cost, and any further dispute with the MTA and state over ownership and cost-sharing.
- As of September 24, 2026 the village says it is waiting for DOT approval of the plans before releasing a bid. Village of Mount Kisco, Preston Way Bridge Closure page · Sep 24, 2026
- A February 2026 agreement with the MTA says the MTA, not the village, pays railroad support costs the MTA estimated at $1.5 million. Village of Mount Kisco, Preston Way Bridge Closure page · Sep 24, 2026
- The village first received a $1.9 million state grant for the bridge in 2018, and the last estimate for the project was about $8.6 million. The Recorder, Village board orders title search over Preston Way bridge ownership