Data centers and city water
Where it standsIn December 2025 the council voted 7-0 to approve a data center in west Shreveport and a water and sewer agreement to serve it.
What's on the tableHow the city oversees data center water use, infrastructure and incentives as the projects are built.
- The water and sewer agreement with TXLAAR, LLC covers a data center campus expected to need up to 7.5 million gallons of potable water a day. Shreveport City Council · Dec 18, 2025
- The council's 7-0 vote approved a special use permit for the data center, overturning the Metropolitan Planning Commission's earlier denial. KSLA · Dec 18, 2025
- The city's interim water director said the treatment plant is rated for almost 80 million gallons a day and averages about 30 million. KSLA · Dec 12, 2025
- Amazon announced plans to invest more than $12 billion in three data center campuses across northwest Louisiana. Louisiana Illuminator · Feb 23, 2026