NE 13th Avenue sidewalks
Where it standsSidewalk construction on NE 13th Avenue is under way, and residents have spoken for and against it at commission meetings in 2026.
What's on the tableWhether to pause or change the sidewalk project for affected homes, and how the city enforces parking where driveways meet new sidewalks.
- On April 14, 2026, Commissioner Budhoo asked that the project be paused at the homes of residents who had expressed concerns; the minutes record Budhoo and Mayor Arnst in favor of a future agenda item for action and three members opposed. City of Oakland Park · Apr 14, 2026 ↗
- At the same meeting, Vice Mayor Gordon discussed the possible risk of breaching the contract by stopping the project. City of Oakland Park · Apr 14, 2026 ↗
- On March 25, 2026, a motion to deny the parking-enforcement policy resolution failed 2-3, and a motion to adopt it died for lack of a second. City of Oakland Park · Mar 25, 2026 ↗
Property tax rate and budget
Where it standsIn July 2026 the commission supported a proposed FY 2027 operating millage rate of 5.6799 mills, with final hearings scheduled for September 2026.
What's on the tableEach year's operating millage rate and budget, including how to prepare for possible state-level property tax cuts.
Horizon downtown project
Where it standsThe commission approved a four-month extension in June 2026, continuing the downtown property sale agreement with Horizon Oakland Park LLC to November 2026.
What's on the tableWhether to keep extending and amending the downtown sale and development agreements, and what the project must deliver.
- On June 17, 2026, the city manager said further changes to the plan would require a neighborhood participation meeting, a development review and a more complete change to the development agreement. City of Oakland Park · Jun 17, 2026 ↗
- On Oct. 22, 2025, the city manager said the county had guaranteed a $5 million up-front grant for downtown improvements and the developer would contribute $1.7 million toward relocating Greenleaf Park. City of Oakland Park · Oct 22, 2025 ↗
- Greenleaf Park opened on Aug. 27, 2026, built with more than $2 million in private investment, ahead of the larger mixed-use project. City of Oakland Park · Sep 4, 2026 ↗
Affordable housing incentives
Where it standsIn February 2026 staff proposed reducing the base permit fee for qualifying affordable projects, with fiscal policy documents to come back for commission approval.
What's on the tableWhether the city offers permit-fee reductions to affordable housing developers, including projects built under the state's Live Local Act.
Communication on city projects
Where it standsResidents asked the commission in 2026 for more communication about construction projects, and the commission announced a community listening session for May 26.
What's on the tableHow the city informs residents about construction timelines, parking impacts and project changes.
- On Jan. 14, 2026, the city manager said staff had done a good job publicizing projects and welcomed suggestions after website update issues. City of Oakland Park · Jan 14, 2026 ↗
- On April 14, 2026, staff said downtown work would bring reduced parking, temporary road closures and event restructuring, and that shuttle and rideshare strategies were being researched. City of Oakland Park · Apr 14, 2026 ↗