The Pittsburg Technology Park data center
Where it standsThe first phase of a 99-megawatt AVAIO data center was approved in 2024 and has not broken ground; phases 2 and 3 are not approved.
What's on the tableWhether to approve later phases and remaining agreements, and whether to set a moratorium or new standards.
- In November 2024 the council certified the project's environmental report, and introduced the specific plan ordinance, both adopted unanimously. Pittsburg City Council minutes, Nov. 4, 2024 · Nov 4, 2024
- City officials said phase one has all land-use approvals, no permits have been issued, and additional agreements still need City Council consideration. Bay Area News Group (Mercury News) · Aug 4, 2026
- In August 2026 the city announced a citizens advisory committee with two councilmembers and 10 to 20 community members to recommend standards for future data centers. Bay Area News Group (Mercury News) · Aug 4, 2026
- The city expects about $2.36 million a year in property and sales taxes from the facility and 30 permanent on-site jobs. Bay Area News Group (Mercury News) · Aug 4, 2026