Where it standsThe council rejected an Airport Drive data center rezoning in May 2026, while a data center at the Wichita Falls Business Park is moving ahead.
What's on the tableThe council will rule on any future rezoning requests, agreements and incentives for data centers.
- The council voted 0-6 on May 5, 2026, against rezoning land on Airport Drive for a data center campus. City Council minutes, May 5, 2026 · May 5, 2026
- The Airport Drive plan would have allowed nine two-story buildings totaling about 1.35 million square feet. City Council minutes, May 5, 2026 · May 5, 2026
- The 4A Economic Development Corporation sold 225 acres at the Wichita Falls Business Park for a data center for $14,625,000. KFDX · Oct 7, 2025