Downtown Mobility Hub
Where it standsThe commission has approved a site plan change and a construction manager for the Mobility Hub at Parking Garage 1; candidates disagree on its scale.
What's on the tableThe next commission will decide how the Mobility Hub proceeds, including its design, financing and artwork.
- The commission voted 4-1 on Feb. 24, 2026 to award the Mobility Hub preconstruction and construction manager contract to Kaufman Lynn Construction. City Commission minutes, 2026-02-24 · Feb 24, 2026
- The commission voted 5-0 on March 10, 2026 to request a $1,000,000 artwork proposal for the Mobility Hub from artist Hernan Bas. City Commission minutes, 2026-03-10 · Mar 10, 2026
- The commission discussed Mobility Hub financing on June 2, 2026; the item was discussed and filed. City Commission minutes, 2026-06-02 · Jun 2, 2026
- Gonzalo Sanabria cites an estimated $70 million cost and a two-year demolition and construction estimate. Coral Gables Gazette · Sep 28, 2026