SDG&E power line route
Where it standsSDG&E and the state grid operator propose a 500-kilovolt line through southern Temecula; the council formally opposed the route in July 2026.
What's on the tableHow hard and how expensively the city fights the route as state regulators review it.
- The Golden Pacific Powerlink would be a new 500-kilovolt transmission line crossing southern Temecula, including the Temecula Creek corridor. City of Temecula agenda report · Jul 14, 2026
- On July 14, 2026, the council voted 5-0 for a resolution opposing the project as proposed through Temecula. Temecula City Council action minutes, July 14, 2026 · Jul 14, 2026
- The California Public Utilities Commission will approve the final route. The Riverside Record · Jul 15, 2026
- The council declared its intent to take legal action and hired attorneys for the case before the CPUC. The Riverside Record · Jul 15, 2026