Antonio Parkway gateway project
Where it standsThe council awarded the main construction contract in December 2024 and the Phase II parkway contract in December 2025.
What's on the tableHow much the city spends on entry monuments, fencing and landscaping, and on their upkeep, in future capital budgets.
- In December 2024 the council awarded a $2,767,430.30 construction contract for the Antonio Parkway Gateway Improvements Project to C.S. Legacy Construction, Inc. (passed 4-1). RSM City Council minutes, Dec. 11, 2024 · Dec 11, 2024
- In August 2025 staff proposed design changes to the parkway phase that it estimated would save $460,000. City staff report, Aug. 13, 2025 · Aug 13, 2025
- In December 2025 the council awarded an $853,444.15 Phase II contract to Marina Landscape, Inc. (passed 3-2). RSM City Council minutes, Dec. 10, 2025 · Dec 10, 2025