Beltline data center
Where it standsThe council voted 4-1 in August 2025 to sell 184.5 acres of city land to BLE Holdings for a proposed data center; a water agreement had not been finalized as of May 2026.
What's on the tableThe council still has to approve a water use agreement and further steps for the project.
- The council voted 4-1 to sell 184.5 acres of city-owned land for $15.8 million to BLE Holdings, LLC of Atlanta. Oklahoma Energy Today, Data center proposed in Yukon · Aug 18, 2025
- Mayor Brian Pillmore explained the city's electric franchise fees would increase $8 million to $12 million a year with the data center in operation. Oklahoma Energy Today, Data center proposed in Yukon · Aug 18, 2025
- BLE has pledged to use only treated wastewater, but an agreement for water service has not yet been finalized. The Yukon Progress, Total Recall · May 9, 2026