Data centers
Where it standsThe council adopted an 18-month data center moratorium on July 20, 2026; motions for a complete ban have been tied or defeated.
What's on the tableThe council will decide what rules, studies or bans follow the moratorium.
- Ordinance 15-26 prohibits data centers in all zones of the borough for 18 months from its adoption. Sayreville Mayor & Council minutes, July 20, 2026 · Jul 20, 2026
- Ordinance 15-26 adopted on second reading by a 5-1 vote on July 20, 2026. Sayreville Mayor & Council minutes, July 20, 2026 · Jul 20, 2026
- On July 20, 2026 a motion to ban data centers completely tied 3-3, and the mayor voted no. Sayreville Mayor & Council minutes, July 20, 2026 · Jul 20, 2026
- The ordinance says the pause is to allow engineering studies on electrical grid, water supply and stormwater capacity, and a fiscal impact analysis. Sayreville Mayor & Council minutes, July 20, 2026 · Jul 20, 2026