Data centers
Where it standsThe council unanimously approved a 45-day moratorium on new data center applications on August 25, 2026.
What's on the tableWhether to extend, replace or lift the pause on data center applications and how to treat any that follow.
- The August 25, 2026 agenda item was an urgency ordinance establishing a 45-day moratorium on accepting and processing new entitlement applications related to data centers. Lake Elsinore City Council agenda, Aug. 25, 2026 · Aug 25, 2026
- Elsinore 247 reported the council approved the moratorium unanimously. Elsinore 247 · Aug 28, 2026
- An applicant representative said a data center is only one of the options being studied for the Elsinore Heights Industrial Project. Elsinore 247 · Jul 30, 2026