Where it standsThe council adopted a 45-day moratorium on data centers on June 3, 2026, and the city is in litigation over the proposed Imperial Data Center.
What's on the tableWhether and how Imperial regulates data centers and similar high-energy projects, and how it handles the ongoing lawsuits.
- The council approved a temporary 45-day moratorium on data centers and other high-energy industrial and technology developments on June 3, 2026, on a 5-0 vote. Calexico Chronicle · Jun 9, 2026
- City staff are to research industry standards and prepare recommendations for permanent zoning regulations during the moratorium. Calexico Chronicle · Jun 9, 2026
- The City of Imperial filed a CEQA lawsuit challenging the review of the Imperial Data Center project. CalMatters
- The developer, Imperial Valley Computer Manufacturing LLC, filed a federal civil rights lawsuit against the city of Imperial and several officials. Calexico Chronicle · Jan 12, 2026